Grantham Southern Relief Road update – New year of works has started

Grantham Southern Relief Road

Works on the second phase of Grantham's new relief road are steadily progressing.

What we achieved in December

  • Continued drainage works to the western side of the scheme
  • Completed piling works / started pile cropping and excavation works in preparation for concrete works for second half of new A1 bridge
  • Continued earthworks across the entire site
  • Carried out planing works and site clearance for signage installation on A1
  • Continued Phase Three Anglian Water watermain diversion and BT ducting
  • Continued post-excavation archaeological reporting

What's happening in January

  • Continue drainage works and earthworks across the entire site
  • Complete pile cropping / start steel and concrete works for second half of new A1 bridge
  • Continue Phase Three Anglian Water watermain/sewer diversions and BT ducting
  • Continue post-excavation archaeological reporting

Upcoming traffic restrictions and closures

  • N/A

Current/ongoing traffic restrictions and closures

  • 50mph speed limit and narrowed lanes on the A1 between Harlaxton to Little Ponton

Published: 4th January 2021