The final 14-tonne and 20-tonne bridge beams for the new A1 connection to the B1174 will be lifted into place later this month
What we achieved in January
- Continued drainage works and earthworks across the entire site
- Completed kerbing works at the eastern roundabout
- Completed pile cropping / started steel and concrete works for second half of new A1 bridge
- Continued Phase Three Anglian Water watermain diversion and BT ducting
- Continued post-excavation archaeological reporting
What's happening in February
- Install the final 14-tonne and 20-tonne bridge beams for the new A1/B1174 connection
- Continue steel and concrete works to the new A1/B1174 connection
- Continue drainage works and earthworks across the entire site
- Continue kerbing across the site, including starting works at the western side of the site
- Begin road surfacing works a the eastern roundabout
- Carry out essential drainage and ducting works to the A1
- Continue Phase Three Anglian Water watermain / sewer diversions and BT ducting
- Continue post-excavation archaeological reporting
Upcoming traffic restrictions and closures
- Full night-time closure on the southbound A1 between Harlaxton and Little Ponton from 8pm to 6am
- Wednesday 10 February to Tuesday 16 February for seven evenings
- Diversion via the A607 at Harlaxton to the A606 to A1 at Stamford.
- Wednesday 10 February to Tuesday 16 February for seven evenings
- Southbound A1 lane closure from Monday 8 February to Tuesday 9 February
- Northbound A1 lane closure from Wednesday 10 February to Wednesday 17 February
- Full night-time closure on the nortbound A1 between Little Ponton and Harlaxton from 8pm to 6am
- Wednesday 17 February to Friday 19 February for three evenings
- Diversion via A606 at Stamford to A607 to A1 at Harlaxton
- Wednesday 17 February to Friday 19 February for three evenings
Current/ongoing traffic restrictions and closures
- 50mph speed limit and narrowed lanes on the A1 between Harlaxton to Little Ponton