What we achieved in March
Phase 4 – from the Co-op access to 182 Roman Bank
- Constructed 65m of new carriageway using 600 tonnes of asphalt
- Constructed 140m of new footpath using 190 tonnes of asphalt and other road building material
- Constructed 4 new property access paths
- Cadent Gas excavated 250m of new trench and laid new gas pipe
- Laid 250m of temporary double-yellow lines on between Brancaster Drive and North Shore Road
Road reconstruction near A52 gyratory
- Removed 80 tonnes of old asphalt and replaced with new
- Laid new white lining
What's happening in April
Phase 4 – from the Co-op access to 182 Roman Bank
- Complete Cadent Gas, Western Power, Anglian Water and BT diversions
- Continue excavating old carriageway and replacing kerbs
Current/ongoing traffic restrictions and closures
- Full road closure between the Co-op access to 182 Roman Bank
Upcoming traffic restrictions and closures
- N/A
Please note that pedestrian access will be maintained for residents and businesses, except when works are being carried directly outside a property (exact location will change as the scheme progresses). Those affected will be notified in advance and are encouraged to speak to the site team to discuss any accommodations that can be made.
Private and on-street parking within the immediate area of works will also be restricted. However, restrictions on two 'limited-time' parking zones on Sea View Road, between the junction with Hoylake Drive and the junction with Roman Bank, will be suspended during the project to provide alternative parking.