Works for May include drainage and ducting across the entire site, installation of bridge foundations, and post evacuation archaeological reporting.
What we achieved in April
Phase Two
- Continued drainage works across the entire site
- Started signage and street light installation
- Began earthworks for the landscaped areas of site
- Started construction of wingwalls for the new A1/B1174 connection
- Carry out drainage and ducting works / install street lighting and signage / carry out surface water channel works on the A1
Phase Three
- Began stripping top soil across the entire site
- Completed spring intercept drainage and continued outfall works
- Continued haul road construction and B1174 ramp works
- Completed site clearance of tree stumps and other remaining vegetation
- Continued post-excavation archaeological reporting
What's happening in May
Phase Two
- Continue drainage and ducting works across the entire site
- Excavate under the new underpass
- Close off and infill the existing underpass
- Carry final bridge deck works and continue tying into the existing carriageway
Phase Three
- Carry out drainage works to the west of the railway
- Continue haul road construction on the west and east sides of site
- Continue B1174 ramp works and piling platforms on the west side of site
- Install haul bridge foundations / complete topsoil stripping / carry out bulk earthworks to the east side of site
- Continue post-excavation archaeological reporting
Current/ongoing traffic restrictions and closures
- 50mph speed limit and narrowed lanes on the A1 between Harlaxton to Little Ponton
- On-going lane closures on the B1174 roundabout until the end of the scheme
Upcoming traffic restrictions and closures
- Occasional off-peak lane restrictions on the B1174 roundabout, as needed