What we achieved in May and what we have planned for June.
Phase Two
- Continued drainage and ducting works across the entire site
- Excavated under the new underpass
- Closed off and infilled the existing underpass
- Carried out final bridge deck works and continue tying into the existing carriageway
Phase Three
- Continued haul road construction on the west and east sides of site
- Continued B1174 ramp works and piling platforms on the west side of site
- Carry out drainage works to the west of the railway
- Carried out bulk earthworks to the east side of site
- Continued post-excavation archaeological reporting
What's happening in June
Phase Two
- Continue drainage and ducting works across the entire site
- Carry out works to underside of new underpass
- Undertake earthworks near the old underpass
- Begin street lighting and signage installation across the entire site
- Road surfacing, lining, ducting and drainage works to the A1
- Remove central reservation on the A1
Phase Three
- Strip topsoil and continue bulk earthworks to the east side of site
- Fill shoulders of site with core material to the east side of site
- Continue haul works / carry out dig and replace works / continue installation of piling platforms / test pile installation to the west side of site
- Continue post-excavation archaeological reporting
Current/ongoing traffic restrictions and closures
- 50mph speed limit and narrowed lanes on the A1 between Harlaxton to Little Ponton
- On-going lane closures on the B1174 roundabout until the end of the scheme
- Southbound A1 closure between Little Ponton and Harlaxton from Wednesday 2 June to Tuesday 3 August, 8pm to 6am
Upcoming traffic restrictions and closures
- Northbound A1 closure between Little Ponton and Harlaxton from Wednesday 4 August to Friday 10 September, 8pm to 6am
- Southbound A1 closure between Little Ponton and Harlaxton from Monday 13 to Friday 17 September, 8pm to 6am
- Northbound A1 closure between Little Ponton and Harlaxton from Monday 20 to Friday 24 September, 8pm to 6am