Holdingham Roundabout update - Saturday leg closures planned for this month

A15 Lincoln new carriageway construction works
A15 Lincoln new carriageway construction works

July will see work begin on the installation of traffic signal ducting, kerb laying and the start of construction of a maintenance track to the central island.

What we achieved in June

  • Completed drainage works to the roundabout's central island and to the A17 dual carriageway ditch
  • Started carriageway widening to A17 West, A17 East and A15 North.
  • Completed Anglian Water diversion/upgrade works and BT cable diversions
  • Completed carriageway reconstruction works on the A15, between Navenby and Brauncewell
  • Traffic diverted to the inner lanes of the roundabout to allow works to progress on its outer perimeter

What's happening in July

  • Begin installation of traffic signals ducting and boxes to central island
  • Start construction of maintenance track to central island
  • Continue installation of streetlight ducting and boxes
  • Lay kerbing on A17 West, A17 East and A15 North.
  • Build laying bituminous sections of road and kerbing to A17 West
  • Continue road reconstruction of A15 between Gorse Hill Lane to Slate House Farm
  • Start road reconstruction on A15/B1429 junction at the Cranwell

Current/ongoing traffic restrictions and closures

  • Temporary 30mph speed restriction and 50mph speed restriction on the A17 dual carriageway
  • Narrowed lanes on the A17 dual carriageway on the approach to the roundabout
  • Reduced lanes on approaches to roundabout during off-peak times
  • Signalised pedestrian crossing facility on A17 and to central roundabout for workforce use
  • Night-time road closures on A15 between Green Man Road and Gorse Hill Lane until early July, 7pm to 6am
  • Pedestrian diversion via the A17 overbridge

Upcoming traffic restrictions and closures

  • One-way closure of A17 Newark (westbound towards Newark) on Saturday 3 July and Saturday 17 July, 7am to 6pm
    • Diversion route via A15 South, A153 West, A607 North
  • Lane closures on the A17 dual carriageway (east of roundabout) for improvement works and grass-cutting on Tuesday 20 and Wednesday 21 July from 9am to 3:30pm
  • One-way closure of A15 Bourne (southbound towards Bourne) on Saturday 7 August and Saturday 14 August, 7am to 6pm
    • Diversion route via A17 West, A607 South, A153 East