Holdingham Roundabout update

Holdingham Roundabout

Surfacing of the roundabout and its legs starts this month

What we achieved in August

  • Continued installation of streetlight ducting and boxes
  • Continued drainage to all legs of the roundabout
  • Continued kerbing on A17 West, A17 East, A15 North and A15 South
  • Completed kerbing between A17 East to B1518 Sleaford
  • Completed rebuilding the widened sections around the roundabout outer circulatory and constructed lower sections of road in the new widened areas
  • Completed road reconstruction on A15, between Navenby and Brauncewell

What's happening in September

  • Continue installation of traffic signal ducting and boxes
  • Commence traffic signal equipment installation
  • Continue installation of streetlight ducting and boxes
  • Begin installing new streetlighting columns
  • Construct kerbing for all new splitter islands
  • Install kerbing on the B1518 (northbound)
  • Begin final surfacing the roundabout circulatory and all of its legs

Current/ongoing traffic restrictions and closures

  • Temporary 30mph speed restriction and 50mph speed restriction on the A17 dual carriageway
  • Reduced lanes on approaches to roundabout during off-peak times
  • Signalised pedestrian crossing facility on A17 and to central roundabout for workforce use
  • Pedestrian diversion via the A17 overbridge

Upcoming traffic restrictions and closures

Published: 1st September 2021