Grantham Southern Relief Road October update

Grantham Southern Relief Road - October Update

A1 works to continue through October

What we achieved in September

Phase Two

  • Continued works to underside of new underpass
  • Continued drainage and ducting works / street lighting and signage installation across the entire site
  • Continue safety barrier installation and began verge works/fencing installation
  • Completed surfacing, including anti-skid treatment, up to northbound off-slip
  • Continued water channel installation and verge works / continue ducting, signage and street light installation on the A1

Phase Three

  • West side of site – filled embankments up to the west embankment / carried out ground investigation works at the bridge piers / began installation of foundational concrete columns for new bridge / started earthworks filling for bridge abutment
  • East side of site – continued rock processing / completed bulk earthworks filling / built construction machinery crossing / started earthworks filling for under bridge abutment
  • Continued post-excavation archaeological reporting

What's happening in October

Phase Two

  • Complete works to underside of new underpass
  • Complete drainage and ducting works / continue street lighting, signage installation and verge works across the entire site
  • Complete safety barrier installation and fencing installation across the entire site
  • Continue surfacing, water channel installation, verge works, ducting, signage and street light installation on the A1

Phase Three

  • West side of site – install new test piles and reaction piles / complete concrete bases and install temporary bridge for pier three / continue general earthworks filling
  • East side of site – continue rock processing and earthworks filling for under bridge abutment / begin construction works to south-west section of Somersby Hill Roundabout
  • Continue post-excavation archaeological reporting

Current/ongoing traffic restrictions and closures

  • 50mph speed limit and narrowed lanes on the A1 between Harlaxton to Little Ponton
  • On-going lane closures on the B1174 roundabout until the end of the scheme

Upcoming traffic restrictions and closures

  • Southbound A1 closure between Little Ponton and Harlaxton from 4-9 October, 11-15 October and 18-22 October from 8pm to 6am
  • Northbound A1 closure between Little Ponton and Harlaxton from 25-29 October, 8pm to 6am
  • Temporary traffic signals and lane closures as needed at Somersby Hill Roundabout from Monday 4 October until Spring 2022

Published: 4th October 2021