Holdingham Roundabout October update

Holdingham Roundabout October update

Roundabout surfacing to be completed this month

What we achieved in September

  • Completed installation of traffic signal ducting and boxes
  • Completed kerbing for all new splitter islands
  • Completed installation of streetlight ducting and boxes
  • Completed construction of all road base material
  • Commenced installing new street-lighting columns
  • Commenced final surfacing the roundabout circulatory and all of its legs

What's happening in October

  • Commence traffic signal equipment installation
  • Erect traffic monitoring cameras
  • Complete kerbing to the B1518 northbound
  • Complete final surfacing of the entire roundabout
  • Complete carriageway markings
  • Complete carriageway traffic signal loops
  • Complete all new drainage
  • Complete installation of all streetlight columns
  • Commence footway construction

Current/ongoing traffic restrictions and closures

  • Temporary 30mph speed restriction and 50mph speed restriction on the A17 dual carriageway
  • Reduced lanes on approaches to roundabout during off-peak times
  • Signalised pedestrian crossing to central roundabout for workforce use
  • Pedestrian diversion via the A17 overbridge

Upcoming traffic restrictions and closures

Published: 4th October 2021