A52 Roman Bank update – 1,500 tonnes of new asphalt laid

Roman bank update

What we achieved in December

Roman Bank – Phases 4B and 5

  • Excavated and disposed of 1,100 tonnes of material
  • Laid 1,500 tonnes of new asphalt
  • Installed new footpath tactile crossings and bollards
  • Broke out and raise ironwork within the road to surface level
  • Repaired existing drainage connections

What's happening in January

Roman Bank – Phases 4B and 5

  • Excavate 100 tonnes of old footpath and replace with asphalt
  • Breakout and re-lay 200m of footpath edgings
  • Replace additional footpath tactile crossings
  • Clean out additional blocked drainage connections

Current/ongoing traffic restrictions and closures

  • Full road closure between the Muirfield Drive and Brancaster Drive junctions on Roman Bank
    • Diversion via the A52 / C541 / A158 at the Gunby dual carriageway, and vice versa.

Please note that pedestrian access will be maintained for residents and businesses, except when works are being carried directly outside a property (exact location will change as the scheme progresses). Those affected will be notified in advance and are encouraged to speak to the site team to discuss any accommodations that can be made.

Private and on-street parking within the immediate area of works will also be restricted.

Published: 4th January 2022