Phase Three works continue forward
What we achieved in January
Phase Two
- Completed installation of street lights and fencing across site
- Completed northbound surfacing works and street light installation on the A1
Phase Three
- West side of site – laid concrete base for the new bridge/sheet piling for pier three / filled the access track at the B1174 roundabout
- East side of site – completed initial surfacing visit at Somerby Hill Roundabout / continued rock processing and main road excavation / continued drainage works
What's happening in February
Phase Two
- Undertake inspections across site
Phase Three
- West side of site – begin main piling works / carry out pile excavation works and cropping / off-site trial erection of bridge pier / continue bridge abutment works
- East side of site – continue east embankment work, including level monitoring / continue rock processing and main road excavation / continue second phase of Somerby Hill roundabout works including additional drainage, ducting, kerbing and surfacing
Current/ongoing traffic restrictions and closures
- 50mph speed limit and narrowed lanes on the A1 between Harlaxton to Little Ponton
- Ongoing lane closures on the B1174 roundabout until the end of the scheme
- Temporary traffic signals and lane closures as needed at Somerby Hill Roundabout until Spring 2022
Upcoming traffic restrictions and closures
- N/A