Weed treatment programme

Below are the dates for our 2023-24 weed treatment programme.

We carry out weed treatment on areas of highway such as footways, cycle tracks, kerb channels and areas of block paved carriageways.  The only exceptions to this are listed below.

District First cut dates Second cut dates
Bostons Borough Council 17 April to 30 April 3 July to 16 July
East Lindsey District Council 1 May to 11 June 17 July to 27 August
North Kesteven District Council 1 May to 4 June 17 July to 20 August
South Holland District Council 17 April to 30 April 3 July to 16 July
South Kesteven District Council 1 May to 4 June 17 July to 20 August
West Lindsey District Council 5 June to 2 July 21 August to 17 September

Areas where weed treatment of the highway is not carried out by us

In the following locations, weed treatment is carried out on our behalf by the parish or town council or, where indicated, the district council. We fund two treatments, with some councils choosing to carry out additional treatments at their own discretion.
 
For further details, including the timing of these treatments, please contact the relevant council directly

Boston Borough

  • Boston town (Boston Borough Council) 

City of Lincoln

  • Lincoln (City of Lincoln Council)

East Lindsey

  • Holton le Clay
  • Horncastle town  

West Lindsey

  • Gainsborough (West Lindsey District Council)
  • Lea (West Lindsey District Council) 
  • Morton (West Lindsey District Council)