What we achieved in October

  • Continued site clearance, fencing, topsoil strip and preparation works across the scheme
  • Continued haul road construction and access works across key sections of the route
  • Progressed bulk excavation and earthworks embankment construction at Grantham Road / Lincoln Cliff and across the scheme
  • Excavated attenuation ponds and drainage ditches across the scheme
  • Continued material processing adjacent to Grantham Road, with reuse of material on other sections
  • Drainage works to ponds, including pipework and headwalls
  • Installation of piped culverts across the scheme
  • Completed piling at Station Road with piles cropped and work started on structure
  • Began piling at River Witham and continued ground improvement piling to west of River Witham
  • Started vegetation clearance around A46 Pennells Roundabout
  • Utilities diversions on Station Road and Brant Road
  • Installation of satellite compounds, powered via solar panels
  • Social value activities carried out, including charity football match raising £600 for hospitals charity, installation of white fencing at Auborn and Haddington boundaries, and attending annual careers fair at Boston Grammar School

What’s happening in November

  • Continue bulk earthworks and embankment construction across the scheme
  • Continue material processing at Grantham Road/Lincoln Cliff and excavation into Lincoln Cliff 
  • Continue drainage works, installation of culverts and pipe work
  • Continue piling works across the project
  • Continue construction of reinforced concrete structure works to Station Road bridge and Wath Lane Accommodation Bridge
  • Continue utility diversions across the scheme
  • Continue mud mitigation measures – two sweepers around the site and manual sweeping of pavement at Station Road
  • Prepare work areas for future construction phases
  • Continue vegetation clearance at A46 roundabout overnight

Current/ongoing traffic restrictions and closures

Upcoming traffic restrictions and closures

  • w/c 2nd November – single lane closure on approaches to A46 Pennells Roundabout for vegetation clearance 
  • Monday 16 November for up to one month – temporary traffic lights on A607 Grantham Road for Anglian Water utility diversions
  • Monday 4 January 2027 for up to seven weeks – 24/7 inbound-only closure on Newark Road, towards Lincoln, at the A46/A1434 Pennells Roundabout
    • Outbound traffic leaving Lincoln will remain open
    • Diversion route via the A46 northbound and the A57/Saxilby Road, with local signage in place to direct traffic travelling to North Hykeham and south Lincoln