Key Build Stage 9 Completed build
The following checks shall be arranged for satisfactory completion.
- Roads and footways swept and cleaned.
- Overall condition of all surfaces, ensuring there are no outstanding defects or temporary reinstatements.
- Any damage to kerbs, channels blocks or edgings.
- Vegetation works complete including:
- Weed growth to be treated.
- Vegetation established and maintained as necessary.
- Grassed verges mown and edged.
- Trees in agreed locations and of acceptable condition.
- Root protection/barrier systems for tree planting.
- Planted areas (including SuDS wildflowers) in agreed locations and of acceptable condition.
- Drainage checks complete including:
- No sediment build up in SuDS features.
- SuDS features are draining effectively.
- No settlement in levels and/or block migration on permeable paving.
- Any permanent water levels in SuDS features are in accordance with the approved design.
- Site SuDS features complete- including those outside of the S38 boundary which serve a highway drainage function.
- Erosion and scour check at surface water discharge point.
- Gullies and drainage systems cleansed.
- Final drainage CCTV survey by certified company for highway drainage (if not supplied prior to this key stage).
- Signs and markings in place.
- Street lighting test certificates supplied and approved.
- Easements are in the correct location, with no encroachments or permanent structures positioned within the area.
- Supporting information:
- Written confirmation to state S104 and/or private foul and surface water drainage systems have been inspected by the responsible party and are without significant defect.
- Request as built drawings to be submitted within the maintenance period.
- Requested that Section 50 applications for privately maintained surface water systems should be submitted.